UK’s superfast broadband arriving very slowly, claims government report
A new report from the National Audit office claims that the much vaunted roll out of superfast broadband to 90 percent of UK households is now two years behind schedule. The programme, seen as vital for the uptake of flexible working in rural areas, is now scheduled for completion in March 2017, around 22 months later than planned. The reasons identified by the NAO for the delays include six months awaiting EU approval along with a range of issues with the procurement of services including those related to the three key principles established to ensure the cost-effectiveness of the programme: the competitive framework; cost transparency; and the terms of supplier contracts. The NAO report claims that of these only the final principle is still functioning. BT is now the only bidder to provide services as others withdrew and it has failed to be sufficiently transparent about its costs.